Treat Calendar and Gantt pages as separate modules. #6153

This will let the Issue Tracking, Gantt, and Calendar modules be enabled
or disabled as needed.  A database migration will enable the Gantt and
Calendar for all existing projects that have Issue Tracking enabled.

Contributed by Adam Soltys

git-svn-id: svn+ssh://rubyforge.org/var/svn/redmine/trunk@4013 e93f8b46-1217-0410-a6f0-8f06a7374b81
This commit is contained in:
Eric Davis committed 2010-08-22 18:42:00 +00:00
1 parent 7e565eed34
commit fc9b984cc1
5 files changed
+57 -4

No files matched your search

@@ -0,0 +1,12 @@
class EnableCalendarAndGanttModulesWhereAppropriate < ActiveRecord::Migration
def self.up
EnabledModule.find(:all, :conditions => ["name = ?", 'issue_tracking']).each do |e|
EnabledModule.create(:name => 'calendar', :project_id => e.project_id)
EnabledModule.create(:name => 'gantt', :project_id => e.project_id)
end
end
def self.down
EnabledModule.delete_all("name = 'calendar' OR name = 'gantt'")
end
end