Precede-Follow relation should move following issues earlier when rescheduling issue earlier (#4590).
git-svn-id: svn+ssh://rubyforge.org/var/svn/redmine/trunk@10878 e93f8b46-1217-0410-a6f0-8f06a7374b81
This commit is contained in:
+35
-1
@@ -1363,7 +1363,7 @@ class IssueTest < ActiveSupport::TestCase
|
||||
end
|
||||
end
|
||||
|
||||
def test_rescheduling_an_issue_should_reschedule_following_issue
|
||||
def test_rescheduling_an_issue_to_a_later_due_date_should_reschedule_following_issue
|
||||
issue1 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
|
||||
issue2 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
|
||||
IssueRelation.create!(:issue_from => issue1, :issue_to => issue2,
|
||||
@@ -1377,6 +1377,40 @@ class IssueTest < ActiveSupport::TestCase
|
||||
assert_equal Date.parse('2012-10-26'), issue2.due_date
|
||||
end
|
||||
|
||||
def test_rescheduling_an_issue_to_an_earlier_due_date_should_reschedule_following_issue
|
||||
issue1 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
|
||||
issue2 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
|
||||
IssueRelation.create!(:issue_from => issue1, :issue_to => issue2,
|
||||
:relation_type => IssueRelation::TYPE_PRECEDES)
|
||||
assert_equal Date.parse('2012-10-18'), issue2.reload.start_date
|
||||
|
||||
issue1.start_date = '2012-09-17'
|
||||
issue1.due_date = '2012-09-18'
|
||||
issue1.save!
|
||||
issue2.reload
|
||||
assert_equal Date.parse('2012-09-19'), issue2.start_date
|
||||
assert_equal Date.parse('2012-09-21'), issue2.due_date
|
||||
end
|
||||
|
||||
def test_rescheduling_reschedule_following_issue_earlier_should_consider_other_preceding_issues
|
||||
issue1 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
|
||||
issue2 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
|
||||
issue3 = Issue.generate!(:start_date => '2012-10-01', :due_date => '2012-10-02')
|
||||
IssueRelation.create!(:issue_from => issue1, :issue_to => issue2,
|
||||
:relation_type => IssueRelation::TYPE_PRECEDES)
|
||||
IssueRelation.create!(:issue_from => issue3, :issue_to => issue2,
|
||||
:relation_type => IssueRelation::TYPE_PRECEDES)
|
||||
assert_equal Date.parse('2012-10-18'), issue2.reload.start_date
|
||||
|
||||
issue1.start_date = '2012-09-17'
|
||||
issue1.due_date = '2012-09-18'
|
||||
issue1.save!
|
||||
issue2.reload
|
||||
# Issue 2 must start after Issue 3
|
||||
assert_equal Date.parse('2012-10-03'), issue2.start_date
|
||||
assert_equal Date.parse('2012-10-05'), issue2.due_date
|
||||
end
|
||||
|
||||
def test_rescheduling_a_stale_issue_should_not_raise_an_error
|
||||
with_settings :non_working_week_days => [] do
|
||||
stale = Issue.find(1)
|
||||
|
||||
Reference in New Issue