Ignore non-working days when rescheduling an issue (#2161).

Weekly non-working days can be configured in application settings (set to saturday and sunday by default).

git-svn-id: svn+ssh://rubyforge.org/var/svn/redmine/trunk@10747 e93f8b46-1217-0410-a6f0-8f06a7374b81
This commit is contained in:
Jean-Philippe Lang
2012-10-29 10:06:30 +00:00
parent 48d83884c3
commit b71355f10b
12 changed files with 244 additions and 19 deletions
+1 -1
View File
@@ -346,7 +346,7 @@ class IssueNestedSetTest < ActiveSupport::TestCase
c1 = Issue.generate!(:start_date => '2010-05-12', :due_date => '2010-05-18', :parent_issue_id => parent.id)
c2 = Issue.generate!(:start_date => '2010-06-03', :due_date => '2010-06-10', :parent_issue_id => parent.id)
parent.reload
parent.reschedule_after(Date.parse('2010-06-02'))
parent.reschedule_on!(Date.parse('2010-06-02'))
c1.reload
assert_equal [Date.parse('2010-06-02'), Date.parse('2010-06-08')], [c1.start_date, c1.due_date]
c2.reload
+71 -12
View File
@@ -1300,22 +1300,81 @@ class IssueTest < ActiveSupport::TestCase
assert !closed_statuses.empty?
end
def test_reschedule_an_issue_without_dates
with_settings :non_working_week_days => [] do
issue = Issue.new(:start_date => nil, :due_date => nil)
issue.reschedule_on '2012-10-09'.to_date
assert_equal '2012-10-09'.to_date, issue.start_date
assert_equal '2012-10-09'.to_date, issue.due_date
end
with_settings :non_working_week_days => %w(6 7) do
issue = Issue.new(:start_date => nil, :due_date => nil)
issue.reschedule_on '2012-10-09'.to_date
assert_equal '2012-10-09'.to_date, issue.start_date
assert_equal '2012-10-09'.to_date, issue.due_date
issue = Issue.new(:start_date => nil, :due_date => nil)
issue.reschedule_on '2012-10-13'.to_date
assert_equal '2012-10-15'.to_date, issue.start_date
assert_equal '2012-10-15'.to_date, issue.due_date
end
end
def test_reschedule_an_issue_with_start_date
with_settings :non_working_week_days => [] do
issue = Issue.new(:start_date => '2012-10-09', :due_date => nil)
issue.reschedule_on '2012-10-13'.to_date
assert_equal '2012-10-13'.to_date, issue.start_date
assert_equal '2012-10-13'.to_date, issue.due_date
end
with_settings :non_working_week_days => %w(6 7) do
issue = Issue.new(:start_date => '2012-10-09', :due_date => nil)
issue.reschedule_on '2012-10-11'.to_date
assert_equal '2012-10-11'.to_date, issue.start_date
assert_equal '2012-10-11'.to_date, issue.due_date
issue = Issue.new(:start_date => '2012-10-09', :due_date => nil)
issue.reschedule_on '2012-10-13'.to_date
assert_equal '2012-10-15'.to_date, issue.start_date
assert_equal '2012-10-15'.to_date, issue.due_date
end
end
def test_reschedule_an_issue_with_start_and_due_dates
with_settings :non_working_week_days => [] do
issue = Issue.new(:start_date => '2012-10-09', :due_date => '2012-10-15')
issue.reschedule_on '2012-10-13'.to_date
assert_equal '2012-10-13'.to_date, issue.start_date
assert_equal '2012-10-19'.to_date, issue.due_date
end
with_settings :non_working_week_days => %w(6 7) do
issue = Issue.new(:start_date => '2012-10-09', :due_date => '2012-10-19') # 8 working days
issue.reschedule_on '2012-10-11'.to_date
assert_equal '2012-10-11'.to_date, issue.start_date
assert_equal '2012-10-23'.to_date, issue.due_date
issue = Issue.new(:start_date => '2012-10-09', :due_date => '2012-10-19')
issue.reschedule_on '2012-10-13'.to_date
assert_equal '2012-10-15'.to_date, issue.start_date
assert_equal '2012-10-25'.to_date, issue.due_date
end
end
def test_rescheduling_an_issue_should_reschedule_following_issue
issue1 = Issue.create!(:project_id => 1, :tracker_id => 1,
:author_id => 1, :status_id => 1,
:subject => '-',
:start_date => Date.today, :due_date => Date.today + 2)
issue2 = Issue.create!(:project_id => 1, :tracker_id => 1,
:author_id => 1, :status_id => 1,
:subject => '-',
:start_date => Date.today, :due_date => Date.today + 2)
issue1 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
issue2 = Issue.generate!(:start_date => '2012-10-15', :due_date => '2012-10-17')
IssueRelation.create!(:issue_from => issue1, :issue_to => issue2,
:relation_type => IssueRelation::TYPE_PRECEDES)
assert_equal issue1.due_date + 1, issue2.reload.start_date
assert_equal Date.parse('2012-10-18'), issue2.reload.start_date
issue1.due_date = Date.today + 5
issue1.due_date = '2012-10-23'
issue1.save!
assert_equal issue1.due_date + 1, issue2.reload.start_date
issue2.reload
assert_equal Date.parse('2012-10-24'), issue2.start_date
assert_equal Date.parse('2012-10-26'), issue2.due_date
end
def test_rescheduling_a_stale_issue_should_not_raise_an_error
@@ -1326,7 +1385,7 @@ class IssueTest < ActiveSupport::TestCase
date = 10.days.from_now.to_date
assert_nothing_raised do
stale.reschedule_after(date)
stale.reschedule_on!(date)
end
assert_equal date, stale.reload.start_date
end
@@ -0,0 +1,76 @@
# Redmine - project management software
# Copyright (C) 2006-2012 Jean-Philippe Lang
#
# This program is free software; you can redistribute it and/or
# modify it under the terms of the GNU General Public License
# as published by the Free Software Foundation; either version 2
# of the License, or (at your option) any later version.
#
# This program is distributed in the hope that it will be useful,
# but WITHOUT ANY WARRANTY; without even the implied warranty of
# MERCHANTABILITY or FITNESS FOR A PARTICULAR PURPOSE. See the
# GNU General Public License for more details.
#
# You should have received a copy of the GNU General Public License
# along with this program; if not, write to the Free Software
# Foundation, Inc., 51 Franklin Street, Fifth Floor, Boston, MA 02110-1301, USA.
require File.expand_path('../../../../../test_helper', __FILE__)
class Redmine::Utils::DateCalculationTest < ActiveSupport::TestCase
include Redmine::Utils::DateCalculation
def test_working_days_without_non_working_week_days
with_settings :non_working_week_days => [] do
assert_working_days 18, '2012-10-09', '2012-10-27'
assert_working_days 6, '2012-10-09', '2012-10-15'
assert_working_days 5, '2012-10-09', '2012-10-14'
assert_working_days 3, '2012-10-09', '2012-10-12'
assert_working_days 3, '2012-10-14', '2012-10-17'
assert_working_days 16, '2012-10-14', '2012-10-30'
end
end
def test_working_days_with_non_working_week_days
with_settings :non_working_week_days => %w(6 7) do
assert_working_days 14, '2012-10-09', '2012-10-27'
assert_working_days 4, '2012-10-09', '2012-10-15'
assert_working_days 4, '2012-10-09', '2012-10-14'
assert_working_days 3, '2012-10-09', '2012-10-12'
assert_working_days 8, '2012-10-09', '2012-10-19'
assert_working_days 8, '2012-10-11', '2012-10-23'
assert_working_days 2, '2012-10-14', '2012-10-17'
assert_working_days 11, '2012-10-14', '2012-10-30'
end
end
def test_add_working_days_without_non_working_week_days
with_settings :non_working_week_days => [] do
assert_add_working_days '2012-10-10', '2012-10-10', 0
assert_add_working_days '2012-10-11', '2012-10-10', 1
assert_add_working_days '2012-10-12', '2012-10-10', 2
assert_add_working_days '2012-10-13', '2012-10-10', 3
assert_add_working_days '2012-10-25', '2012-10-10', 15
end
end
def test_add_working_days_with_non_working_week_days
with_settings :non_working_week_days => %w(6 7) do
assert_add_working_days '2012-10-10', '2012-10-10', 0
assert_add_working_days '2012-10-11', '2012-10-10', 1
assert_add_working_days '2012-10-12', '2012-10-10', 2
assert_add_working_days '2012-10-15', '2012-10-10', 3
assert_add_working_days '2012-10-31', '2012-10-10', 15
assert_add_working_days '2012-10-19', '2012-10-09', 8
assert_add_working_days '2012-10-23', '2012-10-11', 8
end
end
def assert_working_days(expected_days, from, to)
assert_equal expected_days, working_days(from.to_date, to.to_date)
end
def assert_add_working_days(expected_date, from, working_days)
assert_equal expected_date.to_date, add_working_days(from.to_date, working_days)
end
end